ACTIVE ONGOING WORKS ON THE PROJECT «NEW APARTMENT BUILDING AT VĪTOLU STREET 13, LIEPĀJA»
Mar 20
1 min read
Updated: Mar 24
SIA “UPTK” continues construction activities at the project site on Vītolu Street 13.
Currently, structural works are in progress – masonry walls have been completed up to the 3rd floor, and concrete works for floor slabs have also been carried out.
Construction is progressing steadily, and works on site are ongoing.
We thank the surrounding residents for their understanding during the construction process.
This video shows the construction progress of the Vītolu Street 13 project during the period from October 7, 2025 to December 19, 2025. The video highlights the main stages of construction and the ov